Renew Evansville Projects
Wansford Yard Lift Station Phase 1-BC Lift Station Force Main and Pfeiffer Road Interceptor Sewer Project




The lift station force main portion of this project includes the installation of approximately 8,600 feet of new 30" sanitary sewer force main within several city streets from Diamond Avenue to the new Wansford Yard Lift Station located on Harlan Avenue. The work also involves the crossing of Pigeon Creek with associated bank stabilization with articulated concrete block mats, concrete armor masonry units, and high performance turf reinforcement mats.
The Pfeiffer Road interceptor sewer portion of the project includes the installation of approximately 2,000 feet of new 30" gravity sanitary sewer pipe using open cut trenching methods and over 800 feet of gravity sanitary sewer using trenchless methods. The work also includes the installation of 7 new sanitary manhole structures and related sewer bypass pumping to complete the installation between the existing Pfeiffer Road Lift Station to the new Wansford Yard Lift Station on Harlan Avenue.
Project Team
Project Owner
Evansville Water & Sewer Utility
Evansville, Indiana
Design and Construction Engineering Team
Commonwealth Engineers, Inc.
Evansville, Indiana
American Structurepoint, Inc.
Evansville, Indiana
Powers Engineering, Inc.
Evansville, Indinana
CHA Consulting
Evansville, Indiana
CTL Engineering
Indianapolis, Indiana
Contractor
MAC Construction and Excavating, Inc.
New Albany, Indiana

Road Closures
Click HERE for updated road closures.
Project Update
Recent Progress (November 5 to November 11)
-
Division A
-
Bowen continued installing concrete forms for the south wall of wet well (Elev. 350 to Elev. 384).
-
Ft. Wayne Reinforcing installed steel reinforcement bars for the south wall of the wet well level (Elev. 350 to Elev. 384).
-
Bowen installed Grade “B” Borrow backfill around the perimeter of the lift station (to Elev. 350).
-
JH Rudolph installed asphalt pavement patching at the Jail access road.
-
-
Division B
-
MAC began installing new 30” C900 PVC force main on Parkland Avenue between Stringtown Road and Evans Avenue.
-
MAC performed hydrostatic testing of the new 30” C900 PVC force main between Diamond Avenue and Stringtown Road.
-
MAC installed temporary asphalt at the intersection of Stringtown Road and Parkland Avenue.
-
-
Division C
-
MAC completed the installation of new 30” PVC gravity sewer between MH B2-02 (STA. 15+56) and MH B2-03 (STA. 20+31).
-
MAC completed the installation of new precast MH B2-02 (STA. 15+56).
-
Midwest Mole continued installing new 30” gravity sewer by trenchless construction from STA. 35+64 (MH B2-06) to STA. 39+57 (MH B2-07).
-
Anticipated Activities for Upcoming Week (November 12 to November 18)
-
Division A
-
Bowen intends to begin pouring concrete for the south wall of the wet well (Elev. 350 to Elev. 384).
-
Bowen intends to continue installing concrete forms for the south wall of wet well (Elev. 350 to Elev. 384).
-
Ft. Wayne Reinforcing intends to continue installing steel reinforcement bars for the south wall of the wet well level (Elev. 350 to Elev. 384).
-
-
Division B
-
MAC intends to complete the installation of 30” C900 PVC force main on Parkland Avenue between Stringtown Road and Evans Avenue.
-
MAC intends to begin installing new 30” C900 PVC force main on Evans Avenue between Parkland Avenue and Olmstead Avenue.
-
MAC intends to begin HMA pavement restoration between Diamond Avenue and Stringtown Road.
-
-
Division C
-
Midwest Mole intends to continue installing new 30” gravity sewer by trenchless construction from STA. 35+64 (MH B2-06) to STA. 39+57 (MH B2-07).
-
MAC intends to complete the installation of new precast MH B2-03 (STA. 20+31).
-
MAC intends to begin installing new 30” gravity sewer between STA. 20+31 (STA. B2-03) and MH B2-04.
-
MAC intends to perform low pressure air testing on the new 30” gravity sewer between MH B2-01 and MH B2-03.
-
MAC intends to perform vacuum testing of new precast MH B2-01, MH B2-02, and MH B2-03.
-
Road Closures and Lane Restrictions
-
Active
-
Sherman Avenue between Diamond Avenue and Stanley Avenue – Local Traffic Only
-
Parkland Avenue between Stringtown Road and Evans Avenue – Local Traffic Only
-
-
Scheduled
-
No additional closures scheduled at this time.
-
Project Schedule
-
Sherman Avenue, from Diamond Avenue to Negley Avenue
-
Sewer Main Installation – Mid September to Late September 2023
-
Pavement Restoration – Early December to Mid December 2023
-
-
Sherman Avenue, from Negley Avenue to Parkland Avenue
-
Water Main Installation - Ongoing
-
Sewer Main Installation – Late September to Early October 2023
-
Pavement Restoration – Early December to Mid December 2023
-
-
Parkland Avenue, from Sherman Avenue to Stringtown Road
-
Sewer Main Installation – Early October to Mid October 2023
-
Pavement Restoration – Early December to Mid December 2023
-
-
Stringtown Road at Parkland Avenue
-
Sewer Main Installation – Mid October to Late October 2023
-
Pavement Restoration – Early December 2023 to Mid December 2023
-
-
Parkland Avenue, from Stringtown Road to Evans Avenue
-
Sewer Main Installation – Early November to Mid November 2023
-
Pavement Restoration – Early December to Mid December 2023
-
-
Evans Avenue, from Parkland Avenue to Olmstead Avenue
-
Sewer Main Installation – Mid November to Late November 2023
-
Pavement Restoration – Early December to Mid December 2023
-
-
Olmstead Avenue, from Evans Avenue to Kentucky Avenue
-
Sewer Main Installation - Early January to Late March 2024
-
Pavement Restoration – Late March to Mid April 2024
-
-
Kentucky Avenue, from Olmstead Avenue to Idlewild Drive (including Tulip Avenue)
-
Sewer Main Installation - Early January to Late March 2024
-
Water Main Installation – Mid April to Late July 2024
-
Pavement Restoration – Late March to Mid April 2024
-
-
Cardinal Drive, from Idlewild Drive to Bedford Avenue
-
Water Main Installation – Mid April to Late July 2024
-
Sewer Main Installation – Early August to Mid October 2024
-
Pavement Restoration – Mid October to Mid November 2024
-
-
Pigeon Creek Crossing at Cardinal Drive
-
Sewer Main Installation – Mid September to Early November 2023
-
Restoration – Early November 2023
-
-
Sanitary Easement, from Pigeon Creek to Schallers Lane to Wansford Yard Lift Station
-
Sewer Main Installation – Early August to Mid October 2024
-
Gravity Sewer Installation – Late September 2023
-
-
Pfeiffer Road Crossing (by Trenchless Bore)
-
Gravity Sewer Installation – ONGOING
-