Renew Evansville Projects
Wansford Yard Lift Station Phase 1-BC Lift Station Force Main and Pfeiffer Road Interceptor Sewer Project
The lift station force main portion of this project includes the installation of approximately 8,600 feet of new 30" sanitary sewer force main within several city streets from Diamond Avenue to the new Wansford Yard Lift Station located on Harlan Avenue. The work also involves the crossing of Pigeon Creek with associated bank stabilization with articulated concrete block mats, concrete armor masonry units, and high performance turf reinforcement mats.
The Pfeiffer Road interceptor sewer portion of the project includes the installation of approximately 2,000 feet of new 30" gravity sanitary sewer pipe using open cut trenching methods and over 800 feet of gravity sanitary sewer using trenchless methods. The work also includes the installation of 7 new sanitary manhole structures and related sewer bypass pumping to complete the installation between the existing Pfeiffer Road Lift Station to the new Wansford Yard Lift Station on Harlan Avenue.
Project Team
Project Owner
Evansville Water & Sewer Utility
Evansville, Indiana
Design and Construction Engineering Team
Commonwealth Engineers, Inc.
Evansville, Indiana
American Structurepoint, Inc.
Evansville, Indiana
Powers Engineering, Inc.
Evansville, Indinana
CHA Consulting
Evansville, Indiana
CTL Engineering
Indianapolis, Indiana
Contractor
MAC Construction and Excavating, Inc.
New Albany, Indiana
Road Closures
Click HERE for updated road closures.
Project Update
-
Recent Progress (November 10 to November 16)
• Bowen continued repairs to MH B3-01 and HOBAS completed the repairs to the 60” gravity interceptor line (north extension).
• Bowen completed vacuum testing of MH STR. SS-01 on the 24” gravity return line.
• Triangle completed the installation of insulation and stainless-steel jacketing around the HVAC ducts and water lines in the upper screen room and bathroom.
• Bowen continued installing concrete curbs at the lift station site.
• Bowen activated the 8” water main along the south edge of the jail access road.
• Bowen completed the installation of the stainless-steel ladder to the upper roof.
• HTSM completed the installation of the FRP duct to the lower screen room.
• Miller Pipeline completed the installation of the gas service line and gas meter to the lift station building.
• Bowen began installing canopies over the exterior doors.
• Bowen installed the windows on the north side of the lift station building.
-
Anticipated Activities for Upcoming Week (November 17 to November 23)
• Bowen intends to complete repairs to MH B3-01 on the north extension line.
• Bowen intends to continue installing the new 8” C900 PVC gravity sewer between the SMD Garage facility and the north extension.
• Bowen intends to reconnect the new 2” water service to the lift station site, pending the results of water quality sampling.
• High Tech Sheet Metal intends to complete the installation of FRP ductwork to the upper roof.
• Bowen intends to continue installing concrete curbs at the lift station site.
• HFI intends to install a new gas service between the gas meter and the roof.
• Bowen intends to complete the installation of the canopies over the exterior doors.
• Bowen intends to install the brackets for the stilling well.
• Bowen intends to begin working at the Pfeiffer Road lift station (final connections and abandonment).
Road Closures and Lane Restrictions
-
Active
-
No active closures.
-
-
Scheduled
-
No scheduled closures.
-