top of page

Wansford Yard Lift Station Phase 1-BC  Lift Station Force Main and Pfeiffer Road Interceptor Sewer Project

The lift station force main portion of this project includes the installation of approximately 8,600 feet of new 30" sanitary sewer force main within several city streets from Diamond Avenue to the new Wansford Yard Lift Station located on Harlan Avenue.  The work also involves the crossing of Pigeon Creek with associated bank stabilization with articulated concrete block mats, concrete armor masonry units, and high performance turf reinforcement mats.  

The Pfeiffer Road interceptor sewer portion of the project includes the installation of approximately 2,000 feet of new 30" gravity sanitary sewer pipe using open cut trenching methods and over 800 feet of gravity sanitary sewer using trenchless methods.  The work also includes the installation of 7 new sanitary manhole structures and related sewer bypass pumping to complete the installation between the existing Pfeiffer Road Lift Station to the new Wansford Yard Lift Station on Harlan Avenue. 

Project Team

 

Project Owner
Evansville Water & Sewer Utility
Evansville, Indiana

Design and Construction Engineering Team

Commonwealth Engineers, Inc.
Evansville, Indiana

 

American Structurepoint, Inc. 
Evansville, Indiana

Powers Engineering, Inc. 

Evansville, Indinana

CHA Consulting
Evansville, Indiana

 

CTL Engineering
Indianapolis, Indiana

Contractor
MAC Construction and Excavating, Inc. 
New Albany, Indiana

Road Closures

Click HERE for updated road closures.

Project Update​​​
  • Recent Progress (September 1 to September 7)

    • Bowen continued installing the new 60” HOBAS gravity sewer pipe east of MH B3-01 as part of the gravity interceptor sewer extension.

    • Bowen completed the installation of 18” discharge piping and pump bases inside the wet well.

    • Bowen completed the installation of formwork for the 30” header concrete pipe supports inside the valve vault.

    • Bowen continued installing the north slide gates and actuators.

    • Capital Electric continued installing electrical components inside the lift station and valve vault.

    • Midwest Roofing completed the installation of the roof membrane on the lower roof of the lift station.

    • Bartley & Perigo completed the installation of stone masonry around the building exterior.

    • Hi-Tech continued installing FRP duct inside the lift station.

    • Triangle continued installing insulation and steel jacketing around the HVAC ducts inside the lower screen room of the lift station.

    • Parkson performed a soft start-up and conducted training for the mechanical bar screens.

  • Anticipated Activities for Upcoming Week (September 8 to September 14)

    • Bowen intends to continue installing 60” HOBAS pipe east of MH B3-01 as part of the gravity interceptor sewer extension.

    • Bowen intends to complete the installation of concrete pipe supports for the 30” header pipe inside the valve vault.

    • Capital Electric intends to install conduit for the pumps, actuators, and site lighting.

    • Midwest Roofing intends to continue work on the upper roof installation at the lift station.

    • Bowen intends to continue installing the north slide gates and actuators.

    • Robinson Painting intends to begin installing clear coat sealant for the exposed concrete.

    • HFI intends to install water line under the concrete deck.

Road Closures and Lane Restrictions

  • ​Active

    • No active closures.

  • Scheduled​​​ 

    • No closures scheduled.

bottom of page