top of page

Wansford Yard Lift Station Phase 1-BC  Lift Station Force Main and Pfeiffer Road Interceptor Sewer Project

The lift station force main portion of this project includes the installation of approximately 8,600 feet of new 30" sanitary sewer force main within several city streets from Diamond Avenue to the new Wansford Yard Lift Station located on Harlan Avenue.  The work also involves the crossing of Pigeon Creek with associated bank stabilization with articulated concrete block mats, concrete armor masonry units, and high performance turf reinforcement mats.  

The Pfeiffer Road interceptor sewer portion of the project includes the installation of approximately 2,000 feet of new 30" gravity sanitary sewer pipe using open cut trenching methods and over 800 feet of gravity sanitary sewer using trenchless methods.  The work also includes the installation of 7 new sanitary manhole structures and related sewer bypass pumping to complete the installation between the existing Pfeiffer Road Lift Station to the new Wansford Yard Lift Station on Harlan Avenue. 

Project Team

 

Project Owner
Evansville Water & Sewer Utility
Evansville, Indiana

Design and Construction Engineering Team

Commonwealth Engineers, Inc.
Evansville, Indiana

 

American Structurepoint, Inc. 
Evansville, Indiana

Powers Engineering, Inc. 

Evansville, Indinana

CHA Consulting
Evansville, Indiana

 

CTL Engineering
Indianapolis, Indiana

Contractor
MAC Construction and Excavating, Inc. 
New Albany, Indiana

Road Closures

Click HERE for updated road closures.

Project Update​​​
  • Recent Progress (September 22 to September 28)

    • Bowen continued backfilling around the 60” gravity sewer and removing the shoring system.

    • Bowen installed WWF reinforcing for the splash pad sloping grout.

    • Bowen began installing the actuators and stems for the north slide gates.

    • Bowen completed the installation of the covers on the mechanical bar screens and began installing edge rails around the bar screen.

    • Bowen installed the new ladders inside the valve vault and installed earthquake angle.

    • Bowen installed the stainless steel pipe supports for the 18” discharge pipes in the valve vault.

    • Capital Electric continued installing electrical components inside the upper and lower screen rooms including zero speed sensors, conduit in the bathroom and office, conduit for the slide gate actuators, and electrical room.

    • Hi-Tech continued installing FRP duct inside the upper screen room.

    • Triangle continued installing insulation and steel jacketing around the HVAC ducts inside the lower screen room of the lift station.

    • Bowen continued installing the handrail around the opening to the lower screen room.

    • HFI installed plumbing in the new bathroom. 

  • Anticipated Activities for Upcoming Week (September 29 to October 5)

    • Capital Electric intends to continue installing electrical components inside the lower screen room and electrical room, conduit and wiring for the north slide gates, rough in conduit in the bathroom and office, bar screen level sensors, and connect the roof units.

    • Bowen intends to install the pump slide rails, actuator stems, guides, and brackets on the north slide gates, and ladders on the roof

    • Bowen intends to finish welding the handrails around the opening to the lower screen room.

    • Road Safe intends to install traffic control devices for the Pfeiffer Road force main installation.

    • Gribbins intends to begin installing scaffolding at the Pfeiffer Road bridge.

    • Bowen intends to begin installing hangars and pipe supports at the Pfeiffer Road bridge.

    • Triangle intends to install insulation around the HVAC ducts and the water line in the lower screen room.

    • Bowen intends to perform low pressure air testing of the 24” gravity return line.

    • RMK intends to install the sloping grout for the splash pad area.

    • Bowen intends to install 12” RCP storm sewer and set storm sewer inlets and manholes.

    • Robinson intends to install clear coat sealant on the exposed concrete walls.

    • Bowen intends to install backing, drywall ceilings and walls in the bathroom, and install metal walls inside the office

    • Bowen intends to install the concrete pad around the washout structure on the east side of the lift station.

    • Start-ups and training are scheduled to occur for Xylem (pumps), control panels (Toric), Val-Matic (valves), and HP Thompson (slide gates).

    • Badger intends to verify the depths and locations of existing utility crossings for the installation of the 8” water main and SMD force main.

Road Closures and Lane Restrictions

  • ​Active

    • Lane restriction on Pfeiffer Road on or after September 23, 2024.

  • Scheduled​​​ 

    • No scheduled closures.

bottom of page