Lloyd SSRMP Manhole Rehabilitation, Phase 1

This project includes the modification and rehabilitation of 230 existing sanitary sewer manholes in areas south of the Lloyd Expressway and east of Green River Road in Evansville. 

Project Team

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

Project Designer - Evansville Water & Sewer Utility

Evansville, Indiana

Construction Manager - American Structurepoint, Inc. 

Evansville, Indiana

Contractor - Culy Contracting 

Winchester, Indiana

Road Closures

Click HERE for updated road closures.

Project Update

 

Recent Progress (March 5 to March 11)

  • Culy continued manhole lining and bench wall reconstruction in Basins E9-13 and E9-14.

Anticipated Activities for Upcoming Week (March 12 to March 18)

  • Culy intends to continue manhole lining and bench wall reconstruction in Basins E9-14.