This project includes the modification and rehabilitation of the existing lift station wet well as well as the modernization and upgrade of the existing lift station equipment, electrical and control components, and associated equipment. 

Project Team

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

Project Designer - Evansville Water & Sewer Utility

Evansville, Indiana

Construction Manager - American Structurepoint, Inc. 

Evansville, Indiana

Contractor - Culy Contracting 

Winchester, Indiana

Road Closures

Click HERE for updated road closures.

Project Update

 

Recent Progress (November 6  to November 12)

  • No work onsite.

Anticipated Activities for Upcoming Week (November 13 to November 19)

  • No work anticipated.