Lynch Road Large Diameter Lining Project

This project includes CIPP lining approximately 350 feet of 10" diameter sewer main, 3900 feet of 15" diameter sewer main and reconstruction/lining of manholes along Lynch Road from Hitch and Peters to Debbie Lane.

Project Team

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

Project Designer - Evansville Water & Sewer Utility

Evansville, Indiana

Construction Engineering Services - American Structurepoint, Inc. 

Evansville, Indiana

Contractor - Miller Pipeline, LLC

Indianapolis, Indiana

Road Closures

Click HERE for updated road closures.

Project Update
  • Recent Progress (March 31 to April 6)

    • Structured Solutions complete the installation of manhole interior lining systems throughout the Lynch Road project corridor.

    • Structured Solutions completed the benchwall reconstructions throughout the project corridor.

    • Structured Solutions completed the installation of chimney seals throughout the project corridor.​

  • Anticipated Activities for Upcoming Week (April 7 to April 13)

    • No work anticipated on site.

    • Substantial Completion was achieved on April 5, 2024.

  ​​