2022 Annual Lining Hitch and Peters Road

This project includes the modification and rehabilitation of 16 sanitary sewer manholes as as well as the internal lining of approximately 3000 feet of existing sanitary sewer pipe on Hitch and Peters Road between Lynch Road and St. George Road. 

Project Team

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

Project Designer - Evansville Water & Sewer Utility

Evansville, Indiana

Construction Manager - American Structurepoint, Inc. 

Evansville, Indiana

Contractor - Inliner Solutions

Orleans, Indiana

Road Closures

Click HERE for updated road closures.

Project Update

 

Recent Progress 

  • No work onsite. 

Anticipated Activities for Upcoming Week (April 30 to May 6)

  • No work anticipated onsite.  Project is currently scheduled to start in late May.