Toyota Trinity Storm Water Park CSS Separation Project

U1045 Trinity (2)
U1045 Trinity (2)

press to zoom
U1045 Trinity (1)
U1045 Trinity (1)

press to zoom
U1045 Trinity Storm Water Park Downtown NA Preferred Concept
U1045 Trinity Storm Water Park Downtown NA Preferred Concept

press to zoom
U1045 Trinity (2)
U1045 Trinity (2)

press to zoom
1/4

This project includes the installation of a new storm water collection system to separate
the storm water from the combined sanitary sewer in downtown Evansville.  This work will consist of the construction of approximately 4,400 linear feet of 12” to 36” storm sewers, 29 new storm sewer manholes and inlets, as well as the installation of a 1 million gallon subsurface detention basin at the site of the former Holy Trinity Catholic Church located at the intersection of NW 3rd Street and Vine Street. 


The project will also include the replacement of existing water mains within the storm sewer collection system
project area and consists of the replacement of approximately 4,500 linear feet of 6” to 20” water mains, 60 valves, 9 fire hydrants, 19 water service relocations and restoration. 

Project Team

Project Owner

Evansville Water & Sewer Utility

Evansville, Indiana

Project Designers

Beam, Longest & Neff

Evansville, Indiana

United Consulting

Indianapolis, Indiana

Construction Manager

American Structurepoint, Inc. 

Evansville, Indiana

Contractor

Blankenberger Brothers, Inc. 

Cynthiana, Indiana

Road Closures

Click HERE for updated road closures.

Project Update

 

Recent Progress (November 13 to November 19)

  • Blankenberger completed installation of the Court Street chambers.

  • Blankenberger started placement of the embedment stone & final fill for the Court Street chambers.   

  • Blankenberger started installation of the Court manifold in the detention basin.

Anticipated Activities for Upcoming Week (November 20 to November 26)

  • Blankenberger intends to complete placement of the embedment stone and final fill for the Court Street chambers.   

  • Blankenberger intends to close Vine St from NW 3rd St to NW 2nd St to thru traffic.

  • Blankenberger intends to start preliminary pot holing of existing utilities on Vine St.

Active and Scheduled Closures

  • Active

    • ​Vine Street from NW 2nd Street to NW 3rd Street​

  • Scheduled - 11/30/2022

    • NW 2nd Street and Vine Street Intersection

      • Follow Detour to Riverside Drive​

Project Schedule

  • Property Bound by NW 3rd Street, Court Street, NW 4th Street and Vine Street

    • November 2022 to March 2023

  • Vine Street from NW 2nd Street to NW 6th Street

    • December 2022 to March 2023

  • NW 4th Street from Vine Street to Sycamore Street

    • March 2023 to June 2023

  • Sycamore Street from NW5th Street to NW6th Street

    • August 2023 to October 2023

  • Sycamore Street from NW4th Street to NW 3rd Street

    • June 2023 to August 2023

  • NW 5th Street from Vine Street to Sycamore Street

    • March 2023 to June 2023

  • NW 6th Street from Vine Street to Sycamore Street

    • August 2023 to September 2023

  • Cleanup, Miscellaneous Restoration

    • October 2023