top of page

Uhlhorn Street Sewer Rehabilitation

This project includes the repair, replacement, and rehabilitation of approximately 465 feet of 24" sanitary sewer, 735 feet of various sized storm sewer pipe and installation of new structures southwest of the intersection of Uhlhorn Street and First Avenue. 

Project Team

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

Project Designer - Lochmueller Group

Evansville, Indiana

Construction Engineering Services - American Structurepoint, Inc. 

Evansville, Indiana

Contractor - Bowen Engineering

Evansville, Indiana

Road Closures

Click HERE for updated road closures.

Project Update
  • Recent Progress (April 12 to April 18)

    • Bowen mobilized equipment and materials to the project site.

    • Bowen began performing preconstruction documentation.

    • Bowen performed advanced sawcutting and began removing the existing pavement.

    • Bowen began verifying the locations and depths of existing utilities.

    • Bowen connected the new RCP storm sewer to Ex. MH #1069.

    • Bowen began installing 18” RCP storm sewer between Ex. MH #1069 and STR. 204.

  • Anticipated Activities for Upcoming Week (April 19 to April 25) 

    • Bowen intends to continue mobilizing equipment and materials to the project site.

    • Bowen intends to continue installing new 18” RCP storm sewer between Ex. MH #1069 and    STR. 204.

    • Bowen intends to continue verifying the location and depths of existing utilities and identifying potential utility conflicts.

Closures

  • No closures are anticipated. 