Renew Evansville Projects
Uhlhorn Street Sewer Rehabilitation



This project includes the repair, replacement, and rehabilitation of approximately 465 feet of 24" sanitary sewer, 735 feet of various sized storm sewer pipe and installation of new structures southwest of the intersection of Uhlhorn Street and First Avenue.
Project Team
Project Owner - Evansville Water & Sewer Utility
Evansville, Indiana
Project Designer - Lochmueller Group
Evansville, Indiana
Construction Engineering Services - American Structurepoint, Inc.
Evansville, Indiana
Contractor - Bowen Engineering
Evansville, Indiana

Road Closures
Click HERE for updated road closures.
Project Update
-
Recent Progress (April 26 to May 2)
-
Bowen began installing 60” precast barrel sections on existing sanitary sewer manhole STR. 282634.
-
Bowen installed a concrete foundation at existing sanitary sewer manhole STR. 282634.
-
Bowen continued excavating for the installation of new 24” C900 PVC sanitary sewer pipe between existing manhole STR. 282634.
-
Bowen installed HMA base around existing manhole #1069.
-
Bowen performed undercutting on the south side of existing manhole STR. 282634.
-
-
Anticipated Activities for Upcoming Week (May 3 to May 9)
-
Bowen intends to connect the new 24” C900 PVC gravity sewer pipe to existing sanitary sewer manhole STR. 282634.
-
Bowen intends to begin installing new 24” C900 PVC gravity sewer pipe between existing manhole STR. 282634 and sanitary sewer manhole STR. 103.
-
Bowen intends to continue installing new 18” RCP storm sewer between Ex. MH #1069 and STR. 204.
-
Closures
-
No closures are anticipated.