Renew Evansville Projects
Uhlhorn Street Sewer Rehabilitation


This project includes the repair, replacement, and rehabilitation of approximately 465 feet of 24" sanitary sewer, 735 feet of various sized storm sewer pipe and installation of new structures southwest of the intersection of Uhlhorn Street and First Avenue.
Project Team
Project Owner - Evansville Water & Sewer Utility
Evansville, Indiana
Project Designer - Lochmueller Group
Evansville, Indiana
Construction Engineering Services - American Structurepoint, Inc.
Evansville, Indiana
Contractor - Bowen Engineering
Evansville, Indiana

Road Closures
Click HERE for updated road closures.
Project Update
-
Recent Progress (April 12 to April 18)
-
Bowen mobilized equipment and materials to the project site.
-
Bowen began performing preconstruction documentation.
-
Bowen performed advanced sawcutting and began removing the existing pavement.
-
Bowen began verifying the locations and depths of existing utilities.
-
Bowen connected the new RCP storm sewer to Ex. MH #1069.
-
Bowen began installing 18” RCP storm sewer between Ex. MH #1069 and STR. 204.
-
-
Anticipated Activities for Upcoming Week (April 19 to April 25)
-
Bowen intends to continue mobilizing equipment and materials to the project site.
-
Bowen intends to continue installing new 18” RCP storm sewer between Ex. MH #1069 and STR. 204.
-
Bowen intends to continue verifying the location and depths of existing utilities and identifying potential utility conflicts.
-
Closures
-
No closures are anticipated.