top of page

Uhlhorn Street Sewer Rehabilitation

This project includes the repair, replacement, and rehabilitation of approximately 465 feet of 24" sanitary sewer, 735 feet of various sized storm sewer pipe and installation of new structures southwest of the intersection of Uhlhorn Street and First Avenue. 

Project Team

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

Project Designer - Lochmueller Group

Evansville, Indiana

Construction Engineering Services - American Structurepoint, Inc. 

Evansville, Indiana

Contractor - Bowen Engineering

Evansville, Indiana

Road Closures

Click HERE for updated road closures.

Project Update
  • Recent Progress (April 26 to May 2)

    • Bowen began installing 60” precast barrel sections on existing sanitary sewer manhole STR. 282634.

    • Bowen installed a concrete foundation at existing sanitary sewer manhole STR. 282634.

    • Bowen continued excavating for the installation of new 24” C900 PVC sanitary sewer pipe between existing manhole STR. 282634.

    • Bowen installed HMA base around existing manhole #1069.

    • Bowen performed undercutting on the south side of existing manhole STR. 282634.

  • Anticipated Activities for Upcoming Week (May 3 to May 9) 

    • Bowen intends to connect the new 24” C900 PVC gravity sewer pipe to existing sanitary sewer manhole STR. 282634.

    • Bowen intends to begin installing new 24” C900 PVC gravity sewer pipe between existing manhole STR. 282634 and sanitary sewer manhole STR. 103.

    • Bowen intends to continue installing new 18” RCP storm sewer between Ex. MH #1069 and    STR. 204.

Closures

  • No closures are anticipated. 