Renew Evansville Projects
Bergdolt and Oak Hill Road


This project includes the relocation of approximately 430 feet of 8" sanitary sewer main and 5 sanitary sewer manholes at Bergdolt Road and Oak Hill Road.
Project Team
Project Owner - Evansville Water & Sewer Utility
Evansville, Indiana
Project Designer - Evansville Water & Sewer Utility
Evansville, Indiana
Construction Engineering Services - American Structurepoint, Inc.
Evansville, Indiana
Contractor - Deig Bros. Lumber and Construction
Evansville, Indiana

Road Closures
Click HERE for updated road closures.
Project Update
-
Recent Progress (April 26 to May 2)
-
Deig Brothers completed the installation of new 8” C900 PVC sanitary sewer pipe between STR. #200 and STR. #201.
-
Deig Brothers began installing new 8” PVC C-900 sanitary sewer pipe between sanitary sewer manhole STR. #201 and sanitary sewer manhole STR. #202.
-
Deig Brothers completed the installation of new sanitary sewer manhole STR. #201.
-
-
Anticipated Activities for Upcoming Week (May 3 to May 9)
-
Deig Brothers intends to complete the installation of new 8” C900 PVC sanitary sewer pipe between STR. #201 and STR. #202.
-
Deig Brothers intends to complete the installation of new sanitary sewer manhole STR. #202.
-
Deig Brothers intends to begin installing new 8” C900 PVC sanitary sewer pipe between sanitary sewer manholes STR. #202 and STR. #203.
-
Deig intends to complete the installation of new sanitary sewer manhole STR. #203.
-
Closures
-
This project is expected to be a 30-day closure.