Renew Evansville Projects
Eagles Force Main- Phase II




This project includes installation of new 12" force main segments at Morgan Avenue, Oak Grove Road, and Old Boonville Highway along the east side of Crawford-Brandeis Ditch and various gravity sewer improvements.
Project Team
Project Owner - Evansville Water & Sewer Utility
Evansville, Indiana
Project Designer - Commonwealth Engineers, Inc.
Evansville, Indiana
Construction Engineering Services - American Structurepoint, Inc.
Evansville, Indiana
Contractor - Koberstein Contracting, Inc.
Evansville, Indiana

Road Closures
Click HERE for updated road closures.
Project Update
-
Recent Progress (September 6 to September 12)
-
Koberstein installed the base sections of SAN MH 07 and SAN MH 08.
-
Koberstein connected the 12” C900 PVC RJ sanitary sewer carrier pipe to SAN MH 07.
-
Koberstein installed new 12” C900 PVC sanitary sewer pipe between SAN MH 07 and SAN MH 08.
-
Koberstein began installing new 12” C900 PVC force main between the 24” steel casing pipe and the existing sanitary force main on the north side of Morgan Avenue.
-
Koberstein performed site restoration at Old Boonville Highway.
-
-
Anticipated Activities for Upcoming Week (September 13 to September 19)
-
Koberstein intends to begin installing 12” C900 PVC sanitary sewer pipe between SAN MH 08 and SAN MH 10.
-
Koberstein intends to begin installing 12” C900 PVC sanitary sewer pipe between SAN MH 07 and SAN MH 09.
-
Koberstein intends to begin installing SAN MH 05 and SAN MH 06 on the south side of Morgan Avenue.
-
Koberstein intends to begin installing 12” C900 PVC force main on the south side of Morgan Avenue.
-
Closures
-
Active
-
Westbound Morgan Avenue between Burkhardt Road and Royal Avenue - Lane Restriction
-
-
Scheduled
-
Eastbound Morgan Avenue between Wayne's Appliance and Spa City - Lane Restriction on/after 9/23/26
-
Fairfield Drive from Oak Grove to north of IMI -Lane Restriction on/after 9/22/26
-
Schedule
-
Gravity Sewer installation - September 8 to September 11, 2026
-
Force Main installation - September 28 to September 29, 2026
-
Testing and Connections - September 30 to October 6, 2026
-
Abandon Existing facilities - October 7 to October 13, 2026
-
Restoration - October 14 to October 27, 2026