

Renew Evansville Projects
Eagles Force Main- Phase II




This project includes installation of new 12" force main segments at Morgan Avenue, Oak Grove Road, and Old Boonville Highway along the east side of Crawford-Brandeis Ditch and various gravity sewer improvements.
Project Team
Project Owner - Evansville Water & Sewer Utility
Evansville, Indiana
Project Designer - Commonwealth Engineers, Inc.
Evansville, Indiana
Construction Engineering Services - American Structurepoint, Inc.
Evansville, Indiana
Contractor - Koberstein Contracting, Inc.
Evansville, Indiana

Road Closures
Click HERE for updated road closures.
Project Update
-
Recent Progress (October 18 to October 24)
-
Koberstein completed low pressure air testing of the new gravity sewer.
-
Koberstein completed final grading and installed mulched seeding at the Eagles Lift Station and at Morgan Avenue.
-
Koberstein completed the restoration of existing ditches on the north side of Mogan Avenue.
-
-
Anticipated Activities for Upcoming Week (October 25 to October 31)
-
JBI intends to complete the installation of concrete pavement at Old Boonville Highway.
-
Koberstein intends to complete HMA pavement restoration at Oak Grove Road.
-
Koberstein intends to continue performing restoration activity throughout the project site.
-
Closures
-
Active
-
Westbound Morgan Avenue between Burkhardt Road and Royal Avenue - Lane Restriction
-
-
Scheduled
-
No additional closures scheduled at this time.
-
Schedule
-
Gravity Sewer installation - September 8 to September 11, 2026
-
Force Main installation - September 28 to September 29, 2026
-
Testing and Connections - September 30 to October 6, 2026
-
Abandon Existing facilities - October 7 to October 13, 2026
-
Restoration - October 14 to October 27, 2026