top of page

Eagles Force Main- Phase II

This project includes installation of new 12" force main segments at Morgan Avenue, Oak Grove Road, and Old Boonville Highway along the east side of Crawford-Brandeis Ditch and various gravity sewer improvements. 

Project Team

​

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

​

Project Designer - Commonwealth Engineers, Inc.

Evansville, Indiana

​

Construction Engineering Services - American Structurepoint, Inc. 

Evansville, Indiana

​

Contractor - Koberstein Contracting, Inc. 

Evansville, Indiana

​

​

​

Road Closures

Click HERE for updated road closures.

Project Update
  • Recent Progress (October 18 to October 24)

    • Koberstein completed low pressure air testing of the new gravity sewer.

    • Koberstein completed final grading and installed mulched seeding at the Eagles Lift Station and at Morgan Avenue.

    • Koberstein completed the restoration of existing ditches on the north side of Mogan Avenue.

​

  • Anticipated Activities for Upcoming Week (October 25 to October 31) 

    • JBI intends to complete the installation of concrete pavement at Old Boonville Highway.

    • Koberstein intends to complete HMA pavement restoration at Oak Grove Road.

    • Koberstein intends to continue performing restoration activity throughout the project site.

​

Closures

  • Active

    • Westbound Morgan Avenue between Burkhardt Road and Royal Avenue - Lane Restriction​

  • Scheduled

    • No additional closures scheduled at this time. 

​

Schedule

  • Gravity Sewer installation - September 8 to September 11, 2026

  • Force Main installation - September 28 to September 29, 2026

  • Testing and Connections - September 30 to October 6, 2026

  • Abandon Existing facilities - October 7 to October 13, 2026

  • Restoration - October 14 to October 27, 2026

VISITOR COUNT

663

© 2026 American Structurepoint, Inc.

bottom of page