Oak Hill Road, Lynch to St. George


This project includes the relocation of approximately 660 feet of 8" gravity sanitary sewer main and 6 sanitary sewer manholes. It also includes the relocation of approximately 1900 feet of 8" force main on Oak Hill from Lynch to St. George.
Project Team
Project Owner - Evansville Water & Sewer Utility
Evansville, Indiana
Project Designer - Evansville Water & Sewer Utility
Evansville, Indiana
Construction Engineering Services - American Structurepoint, Inc.
Evansville, Indiana
Contractor- Blankenberger Brothers, Inc.
Cynthiana, IN

Road Closures
Click HERE for updated road closures.
Project Update
-
Recent Progress (August 23 to August 29)
-
Blankenberger continued installing new 8” C900 PVC water main on Oak Hill Road between Bergdolt Road and Ivy Meadow Drive.
-
Blankenberger activated the new 8” C900 PVC water main on Oak Hill Road between Elmridge Drive and Aspen Drive.
-
Blankenberger chlorinated the new 8” C900 PVC water main on Oak Hill Road between Aspen Drive and Bergdolt Road.
-
Blankenberger chlorinated the new 4” fire service at 4217 Oak Hill Road.
-
Blankenberger completed the installation of new ¾”-1” water services on Oak Hill Road between Elmridge Drive and Eastbrook Drive.
-
Blankenberger completed the installation of sanitary sewer manholes STR. 301, STR. 302, and STR. 303.
-
Blankenberger completed the installation of new 8” C900 PVC gravity sewer between STR. 301 and STR. 303.
-
Blankenberger began installing new 8” C900 PVC gravity sewer between STR. 303 and STR. 304.
-
-
Anticipated Activities for Upcoming Week (August 30 to September 5)
-
Blankenberger intends to begin the installation of ¾”-1” water services on Oak Hill Road between Eastbrook Drive and Aspen Drive.
-
Blankenberger intends to complete the connection of the new 8” C900 PVC water main to the existing 6” water main on Oak Hill Road at Aspen Drive.
-
Blankenberger intends to complete the connection of the new 8” water main to the existing 4” fire service at 4217 Oak Hill Road, pending the results of water quality sampling.
-
Blankenberger intends to complete the installation of sanitary sewer manholes STR. 304, STR. 305, and STR. 306.
-
Blankenberger intends to complete the installation of new 8” C900 PVC gravity sewer between STR. 303 and STR. 306.
-
Closures
-
Please note this is a Vanderburgh County Road reconstruction project including road improvements and utility relocations that are not affiliated with Evansville Water & Sewer Utility.