top of page

Oak Hill Road, Lynch to St. George 

This project includes the relocation of approximately 660 feet of 8" gravity sanitary sewer main and 6 sanitary sewer manholes. It also includes the relocation of approximately 1900 feet of 8" force main on Oak Hill from Lynch to St. George. 

Project Team

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

Project Designer - Evansville Water & Sewer Utility

Evansville, Indiana

Construction Engineering Services - American Structurepoint, Inc. 

Evansville, Indiana

Contractor- Blankenberger Brothers, Inc.

Cynthiana, IN

Road Closures

Click HERE for updated road closures.

Project Update
  • Recent Progress (August 23 to August 29)

    • Blankenberger continued installing new 8” C900 PVC water main on Oak Hill Road between Bergdolt Road and Ivy Meadow Drive.

    • Blankenberger activated the new 8” C900 PVC water main on Oak Hill Road between Elmridge Drive and Aspen Drive.

    • Blankenberger chlorinated the new 8” C900 PVC water main on Oak Hill Road between Aspen Drive and Bergdolt Road.

    • Blankenberger chlorinated the new 4” fire service at 4217 Oak Hill Road.

    • Blankenberger completed the installation of new ¾”-1” water services on Oak Hill Road between Elmridge Drive and Eastbrook Drive.

    • Blankenberger completed the installation of sanitary sewer manholes STR. 301, STR. 302, and STR. 303.

    • Blankenberger completed the installation of new 8” C900 PVC gravity sewer between STR. 301 and STR. 303.

    • Blankenberger began installing new 8” C900 PVC gravity sewer between STR. 303 and STR. 304.

  • Anticipated Activities for Upcoming Week (August 30 to September 5) 

    • Blankenberger intends to begin the installation of ¾”-1” water services on Oak Hill Road between Eastbrook Drive and Aspen Drive.

    • Blankenberger intends to complete the connection of the new 8” C900 PVC water main to the existing 6” water main on Oak Hill Road at Aspen Drive.

    • Blankenberger intends to complete the connection of the new 8” water main to the existing 4” fire service at 4217 Oak Hill Road, pending the results of water quality sampling.

    • Blankenberger intends to complete the installation of sanitary sewer manholes STR. 304, STR. 305, and STR. 306.

    • Blankenberger intends to complete the installation of new 8” C900 PVC gravity sewer between STR. 303 and STR. 306.

Closures

  • Please note this is a Vanderburgh County Road reconstruction project including road improvements and utility relocations that are not affiliated with Evansville Water & Sewer Utility.

VISITOR COUNT

663

© 2026 American Structurepoint, Inc.

bottom of page