Renew Evansville Projects
Oak Hill Road, Lynch to St. George


This project includes the relocation of approximately 660 feet of 8" gravity sanitary sewer main and 6 sanitary sewer manholes. It also includes the relocation of approximately 1900 feet of 8" force main on Oak Hill from Lynch to St. George.
Project Team
Project Owner - Evansville Water & Sewer Utility
Evansville, Indiana
Project Designer - Evansville Water & Sewer Utility
Evansville, Indiana
Construction Engineering Services - American Structurepoint, Inc.
Evansville, Indiana
Contractor- Blankenberger Brothers, Inc.
Cynthiana, IN

Road Closures
Click HERE for updated road closures.
Project Update
-
Recent Progress (October 18 to October 24)
-
Blankenberger completed the installation of 8” gravity sewer between STR. No. 304 and STR. No. 306.
-
Blankenberger completed the installation of new sanitary sewer manholes STR. No. 305 and STR. No. 306.
-
Blankenberger pigged the new 8” C900 PVC water main between Ridgewood Drive and Bexley Court.
-
Blankenberger performed hydrostatic testing of the new 8” C900 PVC water main Ridgewood Drive and Bexley Court.
-
-
Anticipated Activities for Upcoming Week (October 25 to October 31)
-
Blankenberger intends to re-chlorinate the new 8” C900 PVC water main on Oak Hill Road between Ridgewood Drive and Bexley Court.
-
Blankenberger intends activate the new 8” C900 PVC water main on Oak Hill Road between Ridgewood Drive and Bexley Court, pending the results of water quality sampling.
-
Blankenberger intends to continue the installation of new ¾”-1” water service connections on Oak Hill Road between Ridgewood Drive and Bexley Court, pending the results of water quality sampling.
-
Closures
-
Please note this is a Vanderburgh County Road reconstruction project including road improvements and utility relocations that are not affiliated with Evansville Water & Sewer Utility.