This project includes CIPP lining approximately 530 feet of 8" diameter sewer main, 750 feet of 10" diameter sewer main, 6980 feet of 12" diameter sewer main, 1200 feet of 15" diameter sewer main, 820 feet of 16" diameter sewer main, 2400 feet of 18" diameter sewer main, 530 feet of 24" diameter sewer main, and reconstruction/lining of manholes along Harding Ave. between Morgan and Diamond, and between US 41 and Weinbach Avenue from Keck to Diamond.
Project Team
Project Owner - Evansville Water & Sewer Utility
Evansville, Indiana
Project Designer - Evansville Water & Sewer Utility
Evansville, Indiana
Construction Engineering Services - American Structurepoint, Inc.
Evansville, Indiana
Contractor - Inliner Solutions
Orleans, Indiana
Road Closures
Click HERE for updated road closures.
Project Update
-
Construction is expected to begin on or after December 2, 2024.
Road Closures and Lane Restrictions
-
No closures currently scheduled
Project Schedule
-
Sanitary Sewer Cleaning & Televising – December 2, 2024 to February 3, 2025
-
Sanitary Sewer Pipe Rehabilitation – February 3, 2025 to March 3, 2025
-
Sanitary Sewer Lateral Tap Repairs – February 3, 2025 to February 17, 2025
-
Sanitary Sewer Pipe Repairs – December 9, 2024 to December 11, 2024
-
Sanitary Sewer Manhole Rehabilitation – January 6, 2025 to March 19, 2025
-