This project includes the lining of approximately 10,000 linear feet of sewer main and the rehabilitation of approximately 43 manholes throughout the former Old State Utility Sewer boundary.  Work also includes any necessary pavement restoration, final grading and seeding of the easement areas.  The project is located in northern Vanderburgh County within and near the Shady Hills and Greenbriar Hills subdivisions.  

Project Team

Project Owner - Evansville Water & Sewer Utility

Evansville, IN

Project Designer - Evansville Water & Sewer Utility

Evansville, IN

Construction Manager - American Structurepoint, Inc. 

Evansville, IN

Contractor - Granite Inliner, LLC

Orleans, IN

Road Closures

Click HERE for updated road closures.

Alerts and Announcements

Click HERE for alerts and announcements.

Project Update

Recent Progress 

  • No work onsite. 

 

Anticipated Activities for Upcoming Week (June 12 to June 18)

  • Blankenberger Brothers intends to perform restoration, grading, and seeding.  

  • Culy Contracting intends to perform restoration, grading, and seeding.