Old State Utility Sewer Rehabilitation, Phase 2

old state
old state

press to zoom
old state
old state

press to zoom
1/1

This project includes the lining of approximately 10,000 linear feet of sewer main and the rehabilitation of approximately 43 manholes throughout the former Old State Utility Sewer boundary.  Work also includes any necessary pavement restoration, final grading and seeding of the easement areas.  The project is located in northern Vanderburgh County within and near the Shady Hills and Greenbriar Hills subdivisions.  

Project Team

Project Owner - Evansville Water & Sewer Utility

Evansville, IN

Project Designer - Evansville Water & Sewer Utility

Evansville, IN

Construction Manager - American Structurepoint, Inc. 

Evansville, IN

Contractor - Granite Inliner, LLC

Orleans, IN

Road Closures

Click HERE for updated road closures.

Alerts and Announcements

Click HERE for alerts and announcements.

Project Update

Recent Progress (October 17 to October 23)

  • No work was performed onsite. 

 

Anticipated Activities for Upcoming Month (October 24 to October 30)

  • Granite Inliner intends to continue performing preliminary CCTV inspections on the existing gravity sewer. 

  • Granite Inliner intends to continue cleaning the existing gravity sewer lines. 

  • Granite intends to continue CIPP lining on the southern section map for the project.  

Project Schedule

 

The project schedule will be posted as information is received from the Contractor.