Daylight South Lift Station Rehabilitation

daylight
daylight

daylight
daylight

sewer
sewer

daylight
daylight

1/5

This project includes the modification and rehabilitation of the existing lift station wet well as well as the modernization and upgrade of the existing lift station equipment, electrical and control components, and associated equipment. The project is located in northern Vanderburgh County on the west side of Highway 57, north of Boonville New Harmony Road and south of Schlensker Ditch.  

Project Team

Project Owner - Evansville Water & Sewer Utility

Evansville, IN

Project Designer - Burgess & Niple, Inc.

Indianapolis, IN

Construction Manager - American Structurepoint, Inc. 

Evansville, IN

Contractor - Deig Brothers Lumber and Construction Co., Inc. 

Evansville, IN

Road Closures

Click HERE for updated road closures.

Alerts and Announcements

Click HERE for alerts and announcements.

Project Update

 

Recent Progress (June 6 to June 12)

  • Deig completed the installation of the new permanent 8” bypass connection for use during construction. 

  • Deig completed the installation of the new 12” gate valve assembly. 

Anticipated Activities for Upcoming Month (June 13 to June 19)

  • Deig intends to begin performing bypass pumping operations. 

  • Deig intends to begin installing the 8” and 12” sanitary sewer force main, air release valve, flow meter, and precast structures between the existing control building and the new 8” bypass connection. 

  • Deig intends to begin removal of the existing pumps and components inside the existing lift station. 

Project Schedule

 

The project schedule will be posted as information is received from the Contractor.