This project includes the modification and rehabilitation of the existing lift station wet well as well as the modernization and upgrade of the existing lift station equipment, electrical and control components, and associated equipment. The project is located in northern Vanderburgh County on the west side of Highway 57, north of Boonville New Harmony Road and south of Schlensker Ditch.  

Project Team

Project Owner - Evansville Water & Sewer Utility

Evansville, IN

Project Designer - Burgess & Niple, Inc.

Indianapolis, IN

Construction Manager - American Structurepoint, Inc. 

Evansville, IN

Contractor - Deig Brothers Lumber and Construction Co., Inc. 

Evansville, IN

Road Closures

Click HERE for updated road closures.

Alerts and Announcements

Click HERE for alerts and announcements.

Project Update

 

Recent Progress (July 18 to July 24)

  • Deig backfilled the new 8” ductile iron pump discharge pipe between the wet well and the control building. 

  • Deig began construction of the pump base foundations inside the existing wet well. 

Anticipated Activities for Upcoming Month (July 25 to July 31)

  • Deig intends to continue the installation of the pump bases at the bottom of the wet well. 

  • SpectaTech intends to complete the installation of the interior lining system inside the existing wet well. 

  • Deig intends to continue installing the interior pipe and components in the wet well.