This project includes the modification and rehabilitation of the existing lift station wet well as well as the modernization and upgrade of the existing lift station equipment, electrical and control components, and associated equipment. The project is located in northern Vanderburgh County on the west side of Highway 57, north of Boonville New Harmony Road and south of Schlensker Ditch.  

Project Team

Project Owner - Evansville Water & Sewer Utility

Evansville, IN

Project Designer - Burgess & Niple, Inc.

Indianapolis, IN

Construction Manager - American Structurepoint, Inc. 

Evansville, IN

Contractor - Deig Brothers Lumber and Construction Co., Inc. 

Evansville, IN

Road Closures

Click HERE for updated road closures.

Alerts and Announcements

Click HERE for alerts and announcements.

Project Update

 

Recent Progress (September 12 to September 18)

  • Deig Brothers completed restoration work around the recently completed pavement restoration. 

Anticipated Activities for Upcoming Month (September 19 to September 25)

  • A preliminary punchlist has been scheduled for September 23, 2021.