This project includes the modification and rehabilitation of the existing duplex lift station wet well as well as the modernization and upgrade of the existing lift station equipment, electrical and control components, and associated equipment. 

Project Team

Project Owner - Evansville Water & Sewer Utility

Evansville, IN

Project Designer - Commonwealth Engineers, Inc.

Evansville, IN

Construction Manager - American Structurepoint, Inc. 

Evansville, IN

Contractor - Deig Brothers Lumber and Construction Co., Inc. 

Evansville, IN

Road Closures

Click HERE for updated road closures.

Alerts and Announcements

Click HERE for alerts and announcements.

Project Update

 

Recent Progress (May 23 to May 29) 

  • No work was performed on site. 

Anticipated Activities for Upcoming Week (May 29 to June 5)  

  • No work is anticipated on site this week. 

  • Ragle is awaiting the delivery of the new control panel materials. 

Project Schedule

 