Burdette Park Station Rehabilitation

U1093 Burdette (1)
U1093 Burdette (1)

press to zoom
U1093 Burdette (2)
U1093 Burdette (2)

press to zoom
U1093 Burdette (1)
U1093 Burdette (1)

press to zoom
1/2

This project includes the modification and rehabilitation of the existing lift station wet well as well as the modernization and upgrade of the existing lift station equipment, electrical and control components, and associated equipment. 

Project Team

Project Owner - Evansville Water & Sewer Utility

Evansville, IN

Project Designer - Commonwealth Engineers, Inc.

Evansville, IN

Construction Manager - American Structurepoint, Inc. 

Evansville, IN

Contractor - Koberstein Contracting, Inc. 

Evansville, IN

Road Closures

Click HERE for updated road closures.

Alerts and Announcements

Click HERE for alerts and announcements.

Project Update

 

Recent Progress (May 8 to May 14)

  • Koberstein completed installation the new mezzanine platform for the lift station.

  • Alva Electric mounted the transfer switch.

  • Alva Electric mounted the power junction box for the wet well.

Anticipated Activities for Upcoming Month (May 15 to May 21)

  • Alva Electric intends to complete mounting of all electrical components for the lift station.

  • Alva Electric intends to complete conduit and wiring for the lift station.

  • Koberstein intends to have CenterPoint Energy connect power to the meter for the lift station.