Burdette Park Station Rehabilitation

U1093 Burdette (2)
U1093 Burdette (2)

press to zoom
U1093 Burdette (3)
U1093 Burdette (3)

press to zoom
U1093 Burdette (1)
U1093 Burdette (1)

press to zoom
1/3

This project includes the modification and rehabilitation of the existing lift station wet well as well as the modernization and upgrade of the existing lift station equipment, electrical and control components, and associated equipment. 

Project Team

Project Owner - Evansville Water & Sewer Utility

Evansville, IN

Project Designer - Commonwealth Engineers, Inc.

Evansville, IN

Construction Manager - American Structurepoint, Inc. 

Evansville, IN

Contractor - Koberstein Contracting, Inc. 

Evansville, IN

Road Closures

Click HERE for updated road closures.

Alerts and Announcements

Click HERE for alerts and announcements.

Project Update

 

Recent Progress (June 12 to June 18)

  • Lift station start-up was performed on June 15, 2022.

Anticipated Activities for Upcoming Month (June 19 to June 25)

  • Koberstein intends to complete manhole modifications at the discharge manhole.