Bonnieview and Oak Lift Station Improvements 

Work related to this project includes the Installation of a new sanitary sewer lift station, combination air valve structures, approximately 160 feet of 6” force main, approximately 2,600 feet  of 8” to 24” sized gravity sanitary sewer pipe with 20 sanitary manhole installations varying from 48” to 96” in diameter.  In addition 28 sanitary sewer lateral and cleanouts are planned to be installed, as well as the demolition of the existing lift station and the retirement of existing sanitary sewer facilities.  Areas of installation include: E. Oak Street from Burkhardt to Bonnieview Drive, Bonnieview Drive from Highcroft Drive to Outer Lincoln Avenue.  Additional improvement areas include the installation of new facilities in easements in three areas.  One is bound by Burkhardt, Highcroft, Bonnieview and Oak, while the other area is bound by Bonnieview, Oak and Outer Lincoln Avenue. Minor upgrades are being performed within easement areas immediately south of Cherry Street between Wilson Square and Greenfield Drive.

Project Team

Project Owner - Evansville Water & Sewer Utility

Evansville, IN

Project Designer - Commonwealth Engineers, Inc.

Evansville, IN

Construction Manager - American Structurepoint, Inc. 

Evansville, IN

Contractor - MAC Construction & Excavating, Inc. 

New Albany, IN

Road Closures

Click HERE for updated road closures.

Alerts and Announcements

Click HERE for alerts and announcements.

Project Update

 

Recent Progress (February 14 to February 20)​

  • MAC reopened the intersection of Lincoln and Bonnieview on February 15, 2021.

  • No additional work performed on site this week due to inclement weather.

Anticipated Activities for Upcoming Week (February 21 to February 27) 

  • MAC intends begin performing bypass pumping of the existing wet well.

  • MAC intends to begin converting the existing wet well into a gravity manhole with a manhole liner.

  • MAC intends to install a new concrete ADA ramp on the northwest corner of Lincoln and Bonnieview.

Project Schedule

 

Bonnieview and Oak Lift Station (Bonnieview Drive)

  • Trench and Pit Excavation- Complete

  • Pump Station Construction- Ongoing

  • Restoration- March 2021 to April 2021

 

E. Oak Street, Burkhardt Road to Bonnieview Drive

  • Gravity Sewer Pipe and Manhole Installation- Complete

  • Final Pavement Restoration- March 2021 to April 2021

 

Easement Bound by Burkhardt-Highcroft-Bonnieview-Oak

  • Gravity Sewer Pipe and Manhole Installation- Complete

  • Lawn Restoration- March 2021 to April 2021           

 

Bonnieview Drive, Lincoln Avenue to Bonnieview and Oak Lift Station

  • Gravity Sewer Pipe and Manhole Installation- Complete

  • Final Pavement Restoration- March 2021 to April 2021

 

Easement Bound by Bonnieview-Oak-Lincoln

  • Gravity Sewer Pipe and Manhole Installation- Complete

  • Lawn Restoration- March 2021 to April 2021 

 

Bonnieview Drive, Bonnieview and Oak Lift Station to Highcroft Drive

  • Gravity Sewer Pipe and Manhole Installation- Complete

  • Final Pavement Restoration- March 2021 to April 2021 

 

Easement Bound by Wilson Square, Cherry, Plaza

  • Gravity Sewer Pipe and Manhole Installation- Complete

  • Lawn Restoration- March 2021 to April 2021

© 2017 American Structurepoint, Inc.